|
The Wetherby By-pass and Wharfe Bridge
The small and ancient market town of Wetherby is situated on the north bank of the River Wharfe. There has been a bridge across the river since 1233. The original three arch hump backed bridge was 11 ft. wide.
The by-pass of Wetherby, was opened to traffic on the 26th October 1959. It was the first planned improvement scheme in the country on the Great North Road.
Some 2¼ miles in length, the by-pass starts with the bridge over the River Wharfe and rejoins the Great North Road near the famous Wetherby Race Course.
The contract for the by-pass was let to Crowley Russell and Co. Ltd. In Oct 1957 for the sum of £493,000. The sub-contractors for the Wharfe Bridge were the Cementation Co. Ltd.
The Wharfe Bridge was the first new major bridge to be built in the West Riding. The bridge is of balanced cantilever and suspended span construction, with two side spans each of 96 ft. and a central span of 160 ft., the length of the cantilevers being 45 ft. each with a suspended span of 70 ft.
The bridge was designed in accordance with the requirements of the Ministry of Transport for 45 units of abnormal loading.
The bridge has an angle of skew of 13 degrees. It carries two 24 ft. carriageways, two 8 ft. footpaths, not being a motorway, and a central reservation 10 ft. wide, the width between parapets being 74 ft.
The design for the elevation of the bridge was approved by the Royal Fine Art Commission who took a keen interest in its appearance as the bridge occupies a commanding position in a setting of considerable rural beauty.
The anchor spans and cantilever arms were constructed in reinforced concrete, the deck slab being similarly constructed, and cantilevered out to carry part of each footpath and forming a feature of the elevation.
The central suspended span comprised of pre-stressed post-tensioned concrete beams, with a reinforced concrete deck. Two rectangular fascia beams have curved soffits in profile with the cantilever arms.
The bridge was designed to give a permanent downward force at the abutments under working loads. For ultimate load conditions, 2 in. diameter mild steel eyebolts were provided, dowelled into the mass concrete of the abutments but free to move with expansion and contraction of the bridge. The abutments and wing walls were constructed of mass concrete, taken down to a rock foundation, and faced where exposed with squared snecked rubble masonry.
The two piers are constructed of mass concrete, taken down to a rock foundation just below the level of the river bed. The surface finish to the piers consists of a multiple needle point tooled finish to the concrete which had previously been left with a textured surface provided by means of a special plastic lining to the shuttering.
The balanced cantilever beams, eight in number, are 4 ft. in width and about 17 ft. deep at the piers tapering to the depth of 6 ft. at each abutment and 8 ft. at the outer ends. They are fixed in position at the piers but have freedom of rotation.
The external treatment for the bridge is also a multiple needle point tooled finish.
The deck slab is 12 in. thick throughout being doubly reinforced, and projecting beyond the fascia beams about 4 ft.
The falsework for the cantilever arms was built up on a staging of steel beams carried on timber piles driven into the hard bottom of the river bed. This falsework consisted of tubular steel scaffolding which carried the timber bearers for the cantilever soffit shutters.
The falsework for the anchor arms was of similar construction except that timber piles were only used to carry the scaffolding over the low ground adjacent to the piers. Over the remaining area the tubular scaffolding was built up on mass concrete foundations, or on higher ground, near the abutments, on timber sleepers.
The pre-stressed post-tensioned I-beams were manufactured on site, all cables being pre-stressed before erection except in the case of the outer beams which were partially stressed before erection and finally stressed after construction of the deck slab.
Positioning of the beams was carried out by means of a temporary launching girder. Each beam was carried out on bogies and jacked down into its final position after removing the launching girder sideways.
After the erection of the I beams, transverse diaphragms were cast between the beams and pre-stressed using straight cables. Pre-stressing with the Gifford-Udall system of 0.276in. diameter wires was used throughout.
The eight main beams are supported at mild steel rocker bearings, housed in prefabricated mild steel boxes set into the abutments. The rocker boxes were filled with a soft bitumen to prevent corrosion of the rockers yet allow movements due to temperature changes.
The centre span beams are carried at the fixed end by a pair of 2 in. thick mild steel plates, the lower plate being shaped convexly and fitted with a locating key. At the expansion end, the beams are supported by mild steel rocker bearings. They are housed in bitmen filled prefabricated boxes and set into the transom beam of the cantilevers.
Three expansion joints are provided in the structure, one at each abutment and one at the free end of the 70 ft. suspended span. The expansion joints in the carriageways and footpaths consists of a 2in. butyle rubber strip between two mild steel angles which was compressed until the gap was reduced to 1½ in.
Concrete was made with Quartzite gravels from the Doncaster area from a single source to avoid unpleasant differences of colour and to obtain an appearance after tooling which would blend with the stone of the district.
The exposed faces of the piers and bridge elevations were given a silicone treatment, used for the first time in the West Riding to reduce the effects of grime and road dirt. The damaging effects of the use of de-icing salts not yet having been recorded!
The entire surface area of the deck slab, footpath and central reservation, was covered with a ½in. thick asphalt waterproofing upon which was laid a protective layer of concrete averaging 3in. in thickness.
The construction of the roadworks was not without its problems. Scott records "the ground north of Sandbeck Lane was so bad that we did not strip the turf or top soil. The area was covered with magnesian limestone waste from an old quarry at Collingham which included large blocks of stone.
North of this fill area we went into cutting about 20 ft. deep. When excavating the drainage trench at a depth of 6 to 7 ft. we came across a strong spring which would have been 25 to 30 ft. below the original surface. We put a hopper bottom manhole cover over the spring to collect the water and let it run down the completed drain to the outfall.
The outfall drain was through very bad ground and was laid on a bed of straw and brushwood as it was below the water table. Only two pipe lengths at a time were excavated as the trench would not stand."
The carriageway was surfaced with 3¼ in. of hot rolled asphalt and the footpaths with 1 in. thickness of ¾in. single course tar macadam with a top course of ¼in. fine cold asphalt. In the central reservation the base course consisted of ¾in. single course tar macadam laid 1¼ in. thick.
With the opening of the by-pass in 1959, who could have foreseen that this was to be by-passed some 29 years later in 1988. The final cost of the works was £571,000.
One other event is recorded. The railway bridge adjacent to the Wetherby Racecourse was altered to provide additional clearance for electrification of the Wetherby - York line. The line was closed by Beeching about the time the by-pass opened. |