  1. Recollection, J Tiplady on M11 design decisions, size of contracts, motorway objections and suggestions for increased publicity, October 1997, 4pp

  2. Letter from R Williamson and recollection by B Georgel on M11 Bishop's Stortford to Harlow, Tarmac (now Carrilion Construction) Contract 1973 to 1975, sent 25 June 1998, 2p

  3. List, M11 Contract details, lp

  4. Brochure, M11 London - Cambridge Motorway Contract 1, Redbridge to Loughton, January 1975, 8pp

  5. Brochure,"Contract 3, South Harlow to Bishop's Stortford", October 1974, 8pp

  6. Letter, Robert Phillipson 18 May 1998 and 2 photos by M Francis of M11/M25 Loughton Interchange taken 12 July 1983,lp plus 2 photos

  7. Draft decision letter after Public Inquiry held at Epping between 17 June and 18 July 1969 to inquire into proposals for The M11 London - Cambridge Motorway (Redbridge - Stump Cross Section) Scheme and Side Roads Order, and ancillary orders for The A12 London - Great Yarmouth Trunk Road, The A406 London North Circular Trunk Road and The All London - Norwich Trunk Road, 30pp

  8. Leaflets, A406/North Circular Road, South Woodford to Barking Relief Road, Whole scheme 4pp. Contract 1: (South Woodford to Eastern Avenue), 1985, 5pp and 3 fold; Contract 2: (A12 to A118) , 3 fold; Contract 3: (A118 to A13) 3 fold; Contract 4: (A13 Interchange and Improvement), 3 fold

  9. Statement with plans explaining proposals for A12 Hackney Wick to M11 Link Road, 1987, 8 sided A3 sheet

  10. Brochure, Completing the link between the A12 and the M11, Opened on 6 October 1999, Highways Agency, 22pp

  11. Report, Cambridge Western Bypass, Cambridge Northern Bypass, A604 Improvement (Girton - Godmanchester),Inspector's Report on the Public Inquiry held at Cambridge February 1972 to July 1972, 30 April 1973, 308pp

  12. M11 London - Cambridge Motorway, Public Inquiry, Ministry Proofs of Evidence, 1972, 144pp

  13. Report, The A45 Ipswich - Weedon Trunk Road, (Cambridge Northern Bypass), Findings of Fact. Conclusions and Recommendations of the Inspector's Report on the Public Inquiry held at Cambridge on 4 and 5 March 1975. 55pp (Note: This follows the Joint Public Inquiry into M11 and A45 held in 1972. The A45 was later renumbered as A14.)

  14. Press Cuttings, Cambridge Northern and Western Bypasses, Cambridge Evening News, October 1970 to July 1972, including articles covering each of the 71 days of the Public Inquiry held in 1972

  15. Pamphlet, Cambridge Transport for the 1990's, We need your views, A strategy to cope with traffic in the Cambridge area in the 1990's, 8 sided plus questionnaire

  16. Map, Cambridge Strategy 1990 to 2001, Drawing no J1231/3, Major Road Proposals - Already Planned, New Schemes; Light Rail Proposals: Increased Traffic Restraint; Bus Priority Lanes, 1 no

  17. News Release, EHA146/02, M11 Golden Jubilee Stansted Flyover Opens, Highways Agency/Government News Network East,3pp

  18. Colour Brochure, M11 Motorway, Opening of Stansted Sliproads, December 2002, 4pp

  19. Public Consultation Document, A406 South Woodford to Barking Relief Road, Your views are needed!, Department of the Environment, June 1976, 4 fold with 3 plans