Region: South West
The Aust (J21) to Wickham (J14) section of M4
INDEX TO SECTIONS M4 Almonsbury to Tormarton (J20 to J18) This section of the M4 was let in three separate contracts. The first was from Almondsbury to Hambook including the interchange and the Hambrook Spur road and its connection to the Bristol Ring Road. This contract was awarded, in April 1964, to Sir Alfred McAlpine & Son Ltd.- Leonard Fairclough(AMEC) Ltd. for the sum of £2,342,000 and the works were completed in the contract period of 21 months. The imposing Winterbourne underline steel portal frame bridge carrying the main railway line from London to South Wales was located on this length of the motorway. This was designed by Harry Brompton and Partners and let as a separate contract to A E Farr Ltd in the sum of £ 348,355. With such a busy Railway line which also served Bristol and the North the whole structure had to be rolled into place with limited line occupation. The contract covering the section from Hambrook to Tormarton was also awarded in April 1965 to Sir Alfred McAlpine & Son Ltd.- Leonard Fairclough(AMEC) Ltd. in the sum of £5,277,000 with a contract period of two years. In fact the contract was accelerated so that the road was opened to traffic six months early in tune with the Severn Bridge and the Almondsbury Interchange. On both roadworks contracts the contractor obtained suitable rock for crushing to produce granular sub base and opened borrow pits adjacent to the motorway to win suitable filling materials. The heavy earthworks required at the Cotswold Escarpment were a feature of the second contract where the combination of variable strata in a very deep cutting necessitated the installation of berms for drainage and maintenance purposes. M4 Tormarton to Wootton Bassett (J18 to J16) Let in July 1969, under the auspices of Sir Alexander Gibb & Partners, this was the first contract on the section to complete the M4 between Tormarton and the Maidenhead Bypass. The successful contractor for the 19.2 mile length was Sir Alfred McAlpine and the tender sum was £8,886,105 for a 27 month contract period. The contract included some 3,500,000 cu.yds of earth moving and 1,500,000 cu.yds of imported filling materials. As the contractor decided to obtain quarry materials from the quarry opened on the previous length of motorway the construction commenced with earthworks at the western end. As the start of works was in July every effort was made to progress earthworks rapidly and so much earth moving equipment was brought onto the site that the payment certificates for the September and October amounted to over £1 million. (approaching a quarter of the contract price). At the time the comment was made "No other earth moving equipment is available it's all on "Mc's job"! Another feature of the contract was the 28 bridges which were required. Access in many cases was difficult and the designs relied heavily on precasting of the Superstructure. The process of building therefore demanded highly detailed planning and scheduling of manufacture and delivery. In the words of Bill Egerton "It was a nightmare at times". It is recalled there was a measure of controversy during the design about the merit of using precasting techniques for most of the superstructure of bridges. Whilst the Chief Bridge Engineer in the Ministry of Transport (David Holland) favoured the concept, others considered it more costly and complicated and not so aesthetically pleasing. The progress on the contract was excellent and by early summer 1970 the remaining earthwork was a high embankment at the eastern end where the Motorway crossed the railway. Unfortunately foundations here were very weak and a major ground failure occurred under the embankment which required complete reconstruction with subsequent delay. The first part of the contract was opened in June 1971 to the interchange on the A429 near Hullavington and the remainder opened with the rest of the M4 in December 1971. M4 Liddington to Wickham (J15 to J14) This contract was let to Arthur Monk and Co Ltd. at the end of December 1969 for the tender sum of £7,196,155. The length was 12.2 miles and the tender period was 24 months. The works were located entirely in chalk and required approximately 3,250,000 cu.yds of excavation and over 200,000 cu.yds of imported material. The work was situated high in the Wiltshire and Berkshire downs and included the interchange with the A388 and the Membury Service Area. Monks were an experienced Motorway Contractor, having carried out a number of Motorway projects and their Director, R, Whittle was well known in the Industry as a very knowledgeable contractor. Their Project Manager, Reg Castell, also was well known and had come originally from a structures back ground, having worked for a number of contractors including Tarmac Civil Engineering (now Carrilion Construction) on M5 in Worcestershire. Chalk country is characterized by swallow holes in the strata and this length of Motorway had examples which had to be dealt with. At one bridge site excavations for the foundations exposed a vast cavity which it was decided was a chalk mine and which had to be remedied with large quantities of concrete. No other information of note has been obtained about the difficulties or the success of this section. A more detailed description of the section of the M4 between Holyport (Junction 8/9) and Tormarton (Junction 18), summarised from the opening brochure, can be accessed by clicking here.
Aust to Almondsbury (J21 to J20) - Almondsbury Four Level Interchange (J20) - M4 Almonsbury to Tormarton (J20 to J18) -
M4 Tormarton to Wooten Bassett (J18 to J16) - M4 Wootton Basset to Liddington (J16 to J15) - M4 Liddington To Wickham (J15 to J14)

