Region: North West
Vol 5. M56 Junction 3 Wytheshawe, Manchester to Junction 16, Lea-by-Backford
List of material held in the Cheshire CC Record Office
|
1 |
Design |
||
|
|
1.1 |
Design philosophy by A.Rigby and N.D.Smith |
|
|
|
1.2 |
The North Cheshire East West Motorway Report Volume I Jan 1965 |
|
|
|
1.3 |
The North Cheshire East West Motorway Report Volume II ( Plan Folio ) |
|
|
|
1.4 |
Note by H Mansley |
|
|
|
1.5 |
Itinerary for Landscape Advisory Committee site visit |
|
|
|
1.6 |
Landscape Photographs Princess Parkway Extension |
|
|
|
1.7 |
Landscape Photographs Helsby Frodsham By-Pass Section |
|
|
|
1.8 |
Preliminary Report, Improvement West of Hapsford. November 1968 |
|
|
|
1.9 |
Preston Brook to Bowdon. Firm Programme Report. October 1969 |
|
|
|
1.10 |
Landscape Advisory Committee visit Preston Brook to Bowdon. January 1969 |
|
|
|
1.11 |
Landscape Advisory Committee visit West of Hapsford. January 1967 |
|
|
|
1.12 |
Inspectors Report Preston Brook to Bowdon. July 1970 |
|
|
|
1.13 |
Prelrmmary Report, West of Hapsford. August 1971 |
|
|
|
1.14 |
Landscape Advisory Committee visit West of Hapsford. April 1972 |
|
|
|
1.15 |
Firm Programme Report. West of Hapsford. June 1973 |
|
|
|
1.16 |
Part 1 Inspectors Report. Hapsford to Lea by Backford. August 1974 |
|
|
|
1.17 |
Part 2 Inspectors Report. Hapsford to Lea by Backford. August 1974 |
|
|
|
1.18 |
Wythenshawe-Bowdon Side Roads Order 1968 |
|
|
|
1.19 |
M56 Centre Section Side Road Order. September 1971 |
|
|
|
1.20 |
West of Hapsford Side Road Orders (Draft) |
|
|
2 |
Construction |
||
|
|
2.1 |
Junction 3 Wythenshawe to Junction 9 Bowdon |
|
|
|
|
2.1.1 |
Booklet by Ministry of Transport "North Cheshire Motorway M56 Hapsford to Wythenshawe" |
|
|
|
2.1.2 |
6 No 1/2500 plans of the motorway |
|
|
|
2.1.3 |
Construction Commentary by D.B.Coates, Section Engineer |
|
|
|
2.1.4 |
List of Resident Engineers Staff |
|
|
|
2.1.5 |
Notes by M.A.Selfe, Resident Engineer |
|
|
|
2.1.6 |
Letter to M.A. Selfe with delegation Powers. 31 July 1969 |
|
|
|
2.1.7 |
Letter to Residents re late night working |
|
|
|
2.1.8 |
Report on " Unstable Formation. Ashley Railway Bridge - Cow Lane" |
|
|
|
2.1.9 |
Letter from schoolchildren. |
|
|
|
2.1.10 |
Newspaper cutting. Guardian 16/12/1971 |
|
|
|
2.1.11 |
Newspaper cutting. Daily Mirror 4/1/1972 |
|
|
|
2.1.12 |
Newspaper cutting. Manchester Evening News 4/1/1972 |
|
|
|
2.1.13 |
Newspaper cutting. Daily Mail 4/1/1972 |
|
|
|
2.1.14 |
Newspaper cutting. Contract Journal 6/1/1972 |
|
|
|
2.1.15 |
Paper on site testing by J.H.Bungey former member of the site staff |
|
|
|
2.1.16 |
42 Black and White Photographs during construction |
|
|
2.2 |
Junction 7, Bowdon to Junction 8 M6 |
|
|
|
|
2.2.1 |
Department of the Environment Brochure M56 Preston Brook to Bowdon |
|
|
|
2.2.2 |
Site Plan |
|
|
|
2.2.3 |
Construction Commentary by M.J.Lloyd Chief Resident Engineer |
|
|
|
2.2.4 |
Construction Commentary and cv of J.Reynolds, Contracts Manager |
|
|
|
2.2.5 |
Introduction to the Countryside of the North Cheshire Motorway M56, Centre Section. Unknown Author |
|
|
|
2.2.6 |
Design and Construction details of both the M56 Junctions 7-8 and 8-11. Draft for Brochure? |
|
|
|
2.2.7 |
Proposed Resident Engineers staff establishment - M56 Centre Section. |
|
|
|
2.2.8 |
Resident Engineers Staff Working Hours. C.R.E.Notice 1/72 |
|
|
|
2.2.9 |
County Surveyors Dept. Appointment of Resident Engineer |
|
|
|
2.2.10 |
County Surveyors Dept. Appointment of Section Engineer |
|
|
|
2.2.11 |
Agenda for Progress Meeting No 11 on 29th November 1973 |
|
|
|
2.2.12 |
Names and Addresses of Resident Engineers staff |
|
|
|
2.2.13 |
Commentary Notes used for visit of members of a Professional Institution |
|
|
|
2.2.14 |
Memorial Service for the completion of bridge |
|
|
|
2.2.15 |
10 No Black and White Aerial photographs taken before work commenced |
|
|
|
2.2.16 |
10 No Black and White Aerial Photographs taken during construction |
|
|
2.3 |
Junction 8, M6 to Junction 11, Preston Brook |
|
|
|
|
2.3.1 |
Site Map |
|
|
|
2.3.2 |
Opening Brochure North Cheshire Preston Brook to Bowdon. July 16th 1975 |
|
|
|
2.3.3 |
Construction Report by B.V.Tinsley,Resident Engineer |
|
|
|
2.3.4 |
Hand-written notes by B.J.Robinson on the design details for the drainage on embankments |
|
|
|
2.3.5 |
List of R.E. staff and plan of R.E.offices |
|
|
|
2.3.6 |
Staff notice 7/73 |
|
|
|
2.3.7 |
Staff names and addresses |
|
|
|
2.3.8 |
Summary of principal correspondence prior to Public Inquiry. July 1970 |
|
|
|
2.3.9 |
Report by N.Duncan Consulting Engineer |
|
|
|
2.3.10 |
Observations on the interim assessment of the use of unweathered Keuper Waterstone by B J Robinson 29th 1973 |
|
|
|
2.3.11 |
Engineers Commentary of Marples Ridgway 4 Vol Claim. March 1978 |
|
|
|
2.3.12 |
Engineers Commentary of the Financial Aspects of the Marples Ridgway Claim. March 1978 |
|
|
|
2.3.13 |
Special Appraisal of the Contract. June 1978 |
|
|
|
2.3.14 |
3 no Black and white Aerial Photographs |
|
|
2.4 |
Junction 11 Preston Brook to Junction 14 Hapsford including Advance Contracts |
|
|
|
|
2.4.1 |
Plan of Motorway from Preston Brook to Hapsford |
|
|
|
2.4.2 |
Booklet by Ministry of Transport North Cheshire Motorway M56 Hapsford to Wythenshawe |
|
|
|
2.4.3 |
Advance Preparation Contract Pre Tender discussions |
|
|
|
2.4.4 |
Ministry of Transport Cheshire Subunit, details of Advance and Main Contracts |
|
|
|
2.4.5 |
North Cheshire Motorway M56, Contract Works, Details of Contracts |
|
|
|
2.4.6 |
Construction Report of Advance Contract M 56/1 by M.J.Lloyd, Resident Engineer |
|
|
|
2.4.7 |
Construction Report of Main Contract M 56/5 by M.J.Lloyd, Resident Engineer |
|
|
|
2.4.8 |
Newspaper cutting. Construction News 2/10/1969 |
|
|
|
2.4.9 |
Newspaper cutting. The Guardian ( Chester) Feb 1971 |
|
|
|
2.4.10 |
Newspaper cutting. The Chronicle ( Chester) July 1971 |
|
|
|
2.4.11 |
Newspaper cutting. The Guardian ( Chester) 1971. |
|
|
|
2.4.12 |
Newspaper photograph of Railway Bridge over Motorway near Frodsham. Advance Contract M56 /4 |
|
|
|
2.4.13 |
Results of Plate Bearing Tests Bridge. 26 November 1969 |
|
|
|
2.4.14 |
4 No Black and White Photographs of Railway Bridge over Motorway near Frodsham. Advance Contract M56/4 |
|
|
|
2.4.15 |
180 No Coloured Slides |
|
|
|
2.4.16 |
12 No Black and White Aerial Photographs. Hapsford to the crossing of the River Weaver. April 1969 |
|
|
|
2.4.17 |
Contract details of the Weaver Viaduct |
|
|
|
2.4.18 |
Letter from Dr Keith Best re Weaver Viaduct dated 26th August 1998 |
|
|
|
2.4.19 |
Extracts from book "Best Endeavours" By Dr Keith Best pps 106,107,108,110, 111 |
|
|
|
2.4.20 |
Letter from Dr. Keith Best dated 12th October 1998 |
|
|
|
2.4.21 |
Motorway memories by John Gray, Senior Lands Officer |
|
|
2.5 |
Junction 14, Hapsford to Junction 15, Stoak Interchange |
|
|
|
|
2.5.1 |
Construction Report by M.J.Lloyd |
|
|
|
2.5.2 |
Report on Tenders |
|
|
|
2.5.3 |
Soils report |
|
|
|
2.5.4 |
Letter from the Department of Transport to Contractor dated I3th April 1978 re site staff |
|
|
|
2.5.5 |
Correspondence by Contractor relating to the opening of a quarry at Thornton- le- Moors |
|
|
|
2.5.6 |
Letter from Department of Transport to Contractor dated 30th May 1979 re Monthly Progress Meeting No 8 |
|
|
|
2.5.7 |
Diagrammatic Representation of Volume of Peat excavated from the site of the Motorway |
|
|
|
2.5.8 |
Minutes of Meeting held 19th October 1981 |
|
|
|
2.5.9 |
Accommodation Works Schedule |
|
|
|
2.5.10 |
Report on Progress relating to the settlement of the Final Account dated 30th November 1981 |
|
|
|
2.5.11 |
Letter from Contractor to the Departments of the Environment and Transport, dated 7th January 1997, re settlement of the Final account |
|
|
|
2.5.12 |
Document for the Experimental work on Structures |
|
|
|
2.5.13 |
Experimental work on Structures. Final Account |
|
|
|
2.5.14 |
14 Coloured Photographs. March 2000 |
|
|
2.6 |
Junction 15, Stoak Interchange |
|
|
|
|
2.6.1 |
Plan of Stoak Interchange |
|
|
|
2.6.2 |
Report on Tenders |
|
|
|
2.6.3 |
Accommodation Works Schedule |
|
|
|
2.6.4 |
Contract Details |
|
|
|
2.6.5 |
Construction Report by D.B.Coates. Resident Engineer |
|
|
|
2.6.6 |
8 No Coloured Aerial Photographs. 22 September I980 |
|
|
|
2.6.7 |
10 No Coloured Photographs. March 1981 |
|
|
|
2.6.8 |
Arbitration Documents. 4 Volumes |
|
|
2.7 |
2 .7 Junction 15, Stoak Interchange to Junction 16, Lea - By - Backford |
|
|
|
|
2.7.1 |
Construction Report by B.V.Tinsley |
|
|
|
2.7.2 |
Accommodation Works Schedule |
|
|
|
2.7.3 |
Meeting with the Concrete Advisory Unit. 21 September 1979 |
|
|
|
2.7.4 |
Commentary for slides on the construction of the concrete carriageway |
|
|
|
2.7.5 |
Paper presented to N. W.ICE by Ian Rees. 26th February 1981 |
|
|
|
2.7.6 |
Newspaper cutting "The £500,000 Monster" |
|
|
|
2.7.7 |
Newspaper cutting 13th March 1981. The Observer (Chester) |
|
|
|
2.7.8 |
10 No Coloured Aerial Photographs. 22 September 1980 |
|
|
|
2.7.9 |
36 No Black and White Construction Photographs. 1980 |
|
|
|
2.7.10 |
8 No Coloured photographs prior to opening |
|
|
|
2.7.11 |
Set of Photographs of the Concrete Train and Carriageway |
|
|
|
2.7.12 |
Photograph of the opening Cavalcade |
|
|
|
2.7.13 |
Tickets for Buffet Dance to celebrate the opening of the final stages of the M56 and part of the M531 (Later the M53) |