This fourth report from the NAO on HS2 examines the progress of the programme since 2016; why the schedule is delayed and forecast costs have increased; and the risks that the DfT and HS2 Ltd must manage.
Join other savvy professionals just like you at CIHT. We are committed to fulfilling your professional development needs throughout your career
The report by the National Audit Office published today (24/01/2020) does not seek to conclude whether HS2 ultimately is likely to be value for money, but looks at the cost and schedule estimate in advance of the Department’s plan to take the final investment decision on Phase One of the project. The Department for Transport expects to take the final investment decision on whether to proceed with Phase One and to start main civil construction in early 2020.
Read CIHT's Response to this report here
It is concluded that the The Department, HS2 Ltd and government more widely underestimated the task, leading to optimistic estimates being used to set budgets and delivery dates. In not fully and openly recognising the programme’s risks from the outset, the Department and HS2 Ltd have not adequately managed the risks to value for money.
Read CIHT's Technical Article on cost overruns in megaprojects here.
A total forecast cost for the programme is not yet clear. The Department’s emerging estimate, as at December 2019, gives a potential cost of between £65 billion and £88 billion (2015 prices), between 17% and 58% more than the available funding of £55.7 billion (2015 prices) agreed with HM Treasury.
A number of issues have led to the increased costs:
The report notes that while the estimated cost and schedule for Phase One are now on a stronger footing, the challenge of getting Phase One into construction, and of monitoring and managing the programme as it progresses, is considerable. In going forward, the NAO sets out a number of recommendations for HS2 Ltd and the Department:
On wider programme management issues, the NAO recommends that the government should ensure that it takes appropriate account of the limitations of cost benchmarking information when using this approach to estimate costs.
Source: www.nao.org.uk
CIHT have identified a series of questions we beleive need to be answered to help change the narrative in relation to HS2:
Sue Percy, Chief Executive, CIHT said:
“CIHT has maintained a consistent position in support of the HS2 project as we believe it has clear benefits for capacity, connectivity and the economy if delivered in an appropriate manner. It is clear however, that HS2 is proving to be a divisive issue and more needs to be done to demonstrate the benefits that the project could deliver, including wider regeneration and investment opportunities and the levelling up of the economy.”
CIHT had previously outlined a series of benefits in relation to HS2 that we believe form the basis of rebalancing the current argument.
These benefits included:
CIHT will continue to review the progress of HS2 and discuss in future articles
Join other savvy professionals just like you at CIHT. We are committed to fulfilling your professional development needs throughout your career
{{item.AuthorName}} {{item.AuthorName}} says on {{item.DateFormattedString}}: